NEW QUESTION 15
Which object is used to allocate the costs from a claim to the project structure?

  • A. Network activity
  • B. WBS element
  • C. Claim
  • D. Internal order

Answer: A

 

NEW QUESTION 16
What is the reason for assigning billing plans in customer projects?

  • A. Billing plans are used for revenue planning
  • B. Billing plans are prerequisites for quotation creation
  • C. Billing plans are copied automatically to the sales order item.
  • D. Billing plans enable the billing process to be carried out

Answer: A

 

NEW QUESTION 17
Which orders or documents can be displayed in Project-Oriented Procurement (ProMan)? Note: There are 2 correct Answers to this question.

  • A. Internal orders
  • B. Purchase order items
  • C. Reservations
  • D. Sales order items

Answer: B,C

 

NEW QUESTION 18
What are the prerequisites for delivering materials from the project? Note: There are 2 correct Answers to this question.

  • A. A sold to party is necessary.
  • B. A sales order must be created in advance.
  • C. A shipping point is necessary.
  • D. A delivery document type must be configured.

Answer: A,C

 

NEW QUESTION 19
The basic dates of subordinate WBS elements should be extrapolated without taking into account the basic dates of higher-level WBS elements. What planning method for basic dates do you use?

  • A. Bottom-up
  • B. Free planning
  • C. Top-down
  • D. Strict bottom-up

Answer: A

 

NEW QUESTION 20
You are using budgeting and active availability control. How can availability control be activated? Note:
There are 2 correct Answers to this question.

  • A. Automatic activation with the first actual posting
  • B. Automatic activation with budget assignment
  • C. Automatic activation with assignment to an investment program
  • D. Background activation (CJBV - Activate Availability Control)

Answer: B,D

 

NEW QUESTION 21
In your project, you work with a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well. Now, you increase the quantity of the external activity. How does the system support this scenario?

  • A. The system automatically creates a new purchase requisition with the difference to the original quantity.
  • B. The purchase order can be updated in Goods Receipt for Purchase Order (MIGO).
  • C. The purchase order is updated automatically to match the new quantity while saving the project.
  • D. A workflow can be triggered to inform the purchasing group.

Answer: D

 

NEW QUESTION 22
Where can you assign the user status profile for WBS elements? Note: There are 3 correct Answers to this question.

  • A. In the project version
  • B. In the operative WBS element
  • C. In the project type
  • D. In the project definition of a standard WBS
  • E. In the project profile

Answer: B,D,E

 

NEW QUESTION 23
What are the prerequisites for resource-related billing? Note: There are 2 correct Answers to this question.

  • A. An activity-account-assigned network that is assigned to a sales order item
  • B. A dynamic item processor (DIP) profile with the appropriate settings
  • C. A header-account-assigned network that is assigned to a sales order item
  • D. Released WBS elements, activities, and/or activity elements

Answer: B,D

 

NEW QUESTION 24
You are using networks and external activities in your project. The purchase requisition has been created. What is the sequence for the following business transactions and documents?

  • A. Credit limit check -> Acceptance of performed services -> Vendor selection -> Purchase order handling
    -> Purchase order monitoring -> Goods receipt -> Invoice receipt
  • B. Vendor selection -> Purchase order handling -> Invoice receipt -> Purchase order monitoring -> Goods receipt
  • C. Vendor selection -> Purchase order creation -> Service entry sheet creation -> Service entry sheet approval
  • D. Vendor selection -> Purchase order handling -> Purchase order monitoring -> Goods receipt

Answer: C

 

NEW QUESTION 25
A service company uses project management and they complain that the system does not prevent their project managers from exceeding their budgets. What actions do you have to take to solve the problem?

  • A. Activate availability control in the assigned budget profile. Define the tolerance limits in customizing.
  • B. Activate availability control for the WBS elements. Define the tolerance limits on each WBS element.
  • C. Activate availability control for projects in the controlling area. Enter the plan data for each WBS element.
  • D. Activate commitment management in the project definition. Enter the budget in the master data of the top WBS element.

Answer: A

 

NEW QUESTION 26
You have assigned a budget to WBS elements within your project. What function can be used to check assigned values against the current budget?

  • A. Easy Cost Planning
  • B. Results analysis
  • C. Availability control
  • D. Cost forecast

Answer: C

 

NEW QUESTION 27
Which of the following apply to dynamic item processor (DIP)? Note: There are 3 correct Answers to this question.

  • A. Material determination is mandatory.
  • B. DIP is used to create a quotation.
  • C. Sources can be based on line items.
  • D. Sales prices are maintained in the DIP profile.
  • E. Usage of cost elements is mandatory.

Answer: B,C,D

 

NEW QUESTION 28
Which of the following business processes do NOT lead to the booking of actual costs to an object? Note: There are2 correct answers to this question

  • A. Goods receipt of a non-stock item
  • B. Goods receipt into unvaluated project stock
  • C. Goods receipt into valuated project stock
  • D. Recording of external services in the service entry sheet

Answer: A,D

 

NEW QUESTION 29
You are working with networks and WBS elements. Which of the following statements applies

  • A. You have to maintain a network profile in the project profile
  • B. You have to activate the operative indicator Account Assignment Element for WBS element with activities.
  • C. You can reassign an activity from one network to another
  • D. You can assign the network header to multiple WBS elements

Answer: B

 

NEW QUESTION 30
Which sales documents can update planned revenues on WBS elements? Note: There are 2 correct Answers to this question.

  • A. Inquiry
  • B. Billing
  • C. Sales order
  • D. Quotation

Answer: C,D

 

NEW QUESTION 31
COST AND BUDGET
You have assigned a budget to WBS element with your project
What budget function could be used to check assigned values against the current budget?

  • A. Results analysis
  • B. Easy cost planning
  • C. Availability control
  • D. Cost forecast

Answer: C

 

NEW QUESTION 32
What functions are available for period end closing in SAP Project System? Note: There are 3 correct Answers to this question.

  • A. Confirmations
  • B. Progress analysis
  • C. Results analysis
  • D. Milestone trend analysis
  • E. Settlement

Answer: B,C,E

 

NEW QUESTION 33
......