NEW QUESTION # 13
The project landscape architect suggests reducing the area planned for surface parking and replacing it with additional vegetated space. What benefit would this strategy provide to the owner?

  • A. Increases the rainwater infiltration capacity
  • B. Decreases the required amount of on-street parking that must be provided
  • C. Decreases the amount of bicycle parking that must be provided
  • D. Increases the overall SR (solar reflectance) of the hardscape area

Answer: A


NEW QUESTION # 14
What credit rewards customers who change their normal consumption patterns in response to the varying price of energy over time?

  • A. Energy and Atmosphere Credit, Building Level Energy Metering
  • B. Energy and Atmosphere Credit, Green Power and Carbon Offsets
  • C. Energy and Atmosphere Credit, Demand Response
  • D. Energy and Atmosphere Credit, Advanced Energy Metering

Answer: C

Explanation:
The Energy and Atmosphere Credit, Demand Response rewards projects that participate in demand response programs that aim to reduce peak electricity demand and shift the load to off-peak periods. The LEED v4 Reference Guide for Building Design and Construction states that "the intent of this credit is to increase participation in demand response technologies and programs that make energy generation and distribution systems more efficient, increase grid reliability, and reduce greenhouse gas emissions"1. The project team must either implement a permanent demand response program or develop a plan to implement a program within a year of occupancy. The project team must also demonstrate that the building has the capability to reduce its peak electricity demand by at least 10% in response to demand response signals.
References:
* LEED v4 Reference Guide for Building Design and Construction, Energy and Atmosphere Credit:
Demand Response, page 2721
* Demand response | U.S. Green Building Council2


NEW QUESTION # 15
Which federal agency designates Federal Renewal Community sites, which can be considered High Priority Sites for project development?

  • A. U.S. Department of Agriculture
  • B. U.S. Environmental Protection Agency
  • C. U.S. Internal Revenue Service
  • D. U.S. Department of Housing and Urban Development

Answer: C

Explanation:
Explanation
According to the LEED v4: Building Design + Construction Guide, Federal Renewal Community sites are designated by the U.S. Internal Revenue Service (IRS) as areas that are eligible for tax incentives to encourage businesses to locate and hire residents within the community. These sites are considered High Priority Sites for project development, as they support the revitalization of economically distressed areas. The other federal agencies listed do not designate Federal Renewal Community sites. References: LEED v4: Building Design + Construction Guide, Location and Transportation Credit, High Priority Site, Requirements1; U.S. Internal Revenue Service, Renewal Communities2


NEW QUESTION # 16
What are the requirements of commercial projects for long-term bicycle storage under Location and Transportation, Bicycle Facilities - Bicycle Storage and Shower Rooms?

  • A. Provide for at least 10% of all regular building occupants, with no less than five storage spaces per building
  • B. Provide for at least 15% of all regular building occupants, with no less than 10 storage spaces per building
  • C. Provide for at least 5% of all regular building occupants, with no less than four storage spaces per building
  • D. Provide for at least 25% of all regular building occupants, with no less than 10 storage spaces per building

Answer: A

Explanation:
Explanation
The correct answer is B. Provide for at least 10% of all regular building occupants, with no less than five storage spaces per building.
According to the LEED v4.1 Bicycle Storage Requirements1, commercial projects must provide long-term bicycle storage for at least 10% of all regular building occupants, with no less than five storage spaces per building. Long-term bicycle storage is defined as secure, enclosed, and weather-protected spaces that are intended for use by occupants who make regular trips to the project building. Examples of long-term bicycle storage include lockers, cages, rooms, or dedicated areas within buildings1. The purpose of this requirement is to encourage the use of bicycles as a sustainable mode of transportation and reduce greenhouse gas emissions and fossil fuel consumption.


NEW QUESTION # 17
To achieve the Sustainable Sites Credit, Light Pollution Reduction, Option 1. BUG Rating Method, projects must demonstrate

  • A. all luminaires meet acceptable fixture ratings for the project's Model Lighting Ordnance (MLO) lighting zone
  • B. all luminaires have full cutoff fixtures
  • C. all luminaires are mounted at least three mounting heights from the lighting boundary
  • D. all luminaires have a minimum color temperature of 3500 K

Answer: A

Explanation:
Explanation
To achieve the Sustainable Sites Credit, Light Pollution Reduction, Option 1. BUG Rating Method, projects must demonstrate that all luminaires meet acceptable fixture ratings for the project's Model Lighting Ordnance (MLO) lighting zone. The MLO lighting zone is determined by the site-specific characteristics and the definitions provided in the IES/IDA MLO User Guide1. The fixture ratings are based on the backlight-uplight-glare (BUG) system, which measures the amount of light emitted in different directions by a luminaire, as defined in IES TM-15-11, Addendum A2. The maximum allowable ratings for each lighting zone are given in Table 1 of the credit language3. References: IES/IDA MLO User Guide; IES TM-15-11, Addendum A; Light pollution reduction


NEW QUESTION # 18
A project attempting to meet the preferred parking requirements for Location and Transportation Credit, Green Vehicles may provide what incentive to meet the requirements and highlight the project sustainable vehicle strategy?

  • A. An annual maintenance voucher for at least 5% of occupants driving green vehicles
  • B. Preferred parking decals for 5% of occupants utilizing carpool vehicles
  • C. A permanent discounted parking rate of at least 20% for all green vehicles
  • D. Three years of free parking for green vehicles

Answer: C

Explanation:
Explanation
The Location and Transportation Credit, Green Vehicles aims to reduce transportation-related greenhouse gas emissions by promoting the use of low-emitting, fuel-efficient, and alternative-fuel vehicles1. One of the requirements for this credit is to provide preferred parking for green vehicles for 5% of the total vehicle parking capacity of the project1. Preferred parking is defined as parking that is clearly marked and located in the most convenient spaces available to the driver or nearest to the main entrance of the project2. In addition to providing preferred parking, the project may also offer one or more incentives to encourage the use of green vehicles, such as a discounted parking rate, free parking passes, or rebates for parking fees3. The question asks what incentive may be provided to meet the requirements and highlight the project sustainable vehicle strategy.
The correct answer is C. A permanent discounted parking rate of at least 20% for all green vehicles, because this incentive meets the minimum threshold of 20% discount suggested by the LEED Reference Guide for Building Design and Construction3, and it also demonstrates the project's commitment to supporting green vehicles in the long term. The other options are either not sufficient or not relevant for this credit. Option A.
Three years of free parking for green vehicles is not sufficient because it is not permanent and may not be attractive enough for drivers to switch to green vehicles.
Option B. Preferred parking decals for 5% of occupants utilizing carpool vehicles is not relevant because it does not address green vehicles, but rather carpool vehicles, which are covered by a different credit (Location and Transportation Credit, Reduced Parking Footprint)4. Option D. An annual maintenance voucher for at least 5% of occupants driving green vehicles is not sufficient because it is not directly related to parking and may not be a significant incentive for drivers.
References:
* Green Vehicles
* Green Vehicles - Canada Green Building Council
* [LEED Reference Guide for Building Design and Construction v4], page 544
* Reduced Parking Footprint


NEW QUESTION # 19
Innovation credits for exemplary performance can be awarded for

  • A. demonstrating a qualitative improvement in environmental performance
  • B. demonstrating significant environmental benefits
  • C. achieving double the credit requirements
  • D. achieving one pilot credit

Answer: C

Explanation:
Explanation
Exemplary performance credits are one of the options to earn innovation points under the LEED v4.1 rating system. They are typically awarded for achieving double the credit requirements or the next incremental percentage threshold of an existing LEED v4.1 prerequisite or credit that allows exemplary performance. For example, to earn an exemplary performance point for the Energy and Atmosphere credit Optimize Energy Performance, the project must demonstrate a percentage improvement in the proposed building performance rating compared to the baseline building performance rating per ASHRAE 90.1-2010 by at least 12 percentage points for new construction, or by at least 16 percentage points for major renovations.
References: = NC-v4.1 INc1: Innovation | LEEDuser, Guide to Exemplary Performance Credits in LEED-NC v4 | LEEDuser


NEW QUESTION # 20
Which of the following Sustainable Sites credits are eligible to be used as a campus approach?

  • A. Light Pollution Reduction, Places of Respite, Open Space
  • B. Heat Island Reduction, Light Pollution Reduction, Rainwater Management
  • C. Heat Island Reduction, Places of Respite, Site Master Plan
  • D. Direct Exterior Access, Heat Island Reduction, Rainwater Management

Answer: B

Explanation:
Explanation
According to the LEED Campus Guidance, the campus approach allows projects that share a single location and site attributes to achieve separate LEED certification for each project, building space, or group on the master site. The campus approach can be used for certain credits that are influenced by the site conditions and infrastructure, such as Sustainable Sites credits. The LEED Campus Guidance provides a list of eligible credits for the campus approach, which includes the following Sustainable Sites credits1:
*Site Assessment
*Site Development - Protect or Restore Habitat
*Open Space
*Rainwater Management
*Heat Island Reduction
*Light Pollution Reduction
Therefore, Heat Island Reduction, Light Pollution Reduction, and Rainwater Management are Sustainable Sites credits that are eligible to be used as a campus approach. Places of Respite, Site Master Plan, and Direct Exterior Access are not Sustainable Sites credits, but other credits or prerequisites that are not eligible for the campus approach1.
References:
*LEED Campus Guidance1


NEW QUESTION # 21
Which of the following characteristics are a requirement of a compliant water meter?

  • A. Must be digital
  • B. Must be permanently installed
  • C. Must be capable of storing data for 36 months
  • D. Must transmit data to a remote location

Answer: B

Explanation:
Explanation
A compliant water meter is a device that measures and records the total potable water use of the building and associated grounds. According to the LEED v4 Reference Guide for Building Design and Construction, a compliant water meter must meet the following requirements1:
*It must be permanently installed and measure the total water use of the building and grounds.
*It must have a remote communication capability or be readable from a location that is accessible to building management.
*It must have a data storage capability of at least 18 months, or be connected to a system that can store data for at least 18 months.
*It must have a resolution of 0.5 gallons (2 liters) or less, or the smallest unit of measure that is appropriate for the expected water use of the building.
References:
*LEED v4 Reference Guide for Building Design and Construction, Water Efficiency Prerequisite:
Building-Level Water Metering, page 3781
*Water metering | U.S. Green Building Council


NEW QUESTION # 22
The project team wants to modify the design of an office building copy room to minimize the risk of airborne contamination to the surrounding space. The design includes a separate exhaust, but due to design constraints the partition walls of the room cannot run deck-to-deck. What can the team do to achieve Indoor Environmental Quality Credit, Enhanced Indoor Air Quality Strategies?

  • A. Use MERV 8 (F5), or higher, filters
  • B. Provide a hard-lid ceiling
  • C. Create positive pressure in the room
  • D. Provide a large opening to dilute air contaminates

Answer: B

Explanation:
Explanation
The Indoor Environmental Quality Credit, Enhanced Indoor Air Quality Strategies aims to establish better quality indoor air for the building occupants that promotes their comfort and well-being1. This credit requires the project team to implement several strategies to reduce the exposure of occupants and HVAC systems to environmental tobacco smoke, airborne contaminants, and chemicals1. One of the strategies is to design and construct all interior partitions to full height (deck-to-deck) or provide a hard-lid ceiling for spaces where hazardous gases or chemicals may be present or used2. This strategy helps prevent the migration of contaminants from one space to another through the plenum3. A copy room is an example of such a space, as it may contain printers, copiers, toners, and solvents that can emit volatile organic compounds (VOCs) and particulate matter (PM) into the air4. Therefore, the project team can achieve Indoor Environmental Quality Credit, Enhanced Indoor Air Quality Strategies by providing a hard-lid ceiling for the copy room.
References:
Enhanced Indoor Air Quality Strategies
Enhanced Indoor Air Quality Strategies - Canada Green Building Council
[LEED Reference Guide for Building Design and Construction v4], page 631 Copy Rooms: A Source of Indoor Air Pollution


NEW QUESTION # 23
A Photovoltaic (PV) system was installed on a 35,000 ft2 (3 252 m2) project. What actions need to take place in order to meet compliance for Energy and Atmosphere Prerequisite, Fundamental Commissioning (Cx) and Verification?

  • A. No action is necessary as the PV system is not required to be commissioned
  • B. The PV system installer should commission his own installations and share the results with the project owner
  • C. The building's mechanical engineer should commission his own installations and share the results with the project owner
  • D. The Cx agent for the project must conduct or oversee the Cx of the PV system

Answer: D

Explanation:
Explanation
The correct answer is C, the Cx agent for the project must conduct or oversee the Cx of the PV system.
According to the LEED v4 Reference Guide for Building Design and Construction, the Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification, requires that all energy-related systems, including renewable energy systems such as PV, be commissioned by an independent commissioning agent (CxA) or a qualified member of the project team who reports to the owner. The CxA or the qualified team member must perform or oversee all commissioning activities, including developing a commissioning plan, reviewing design documents and submittals, verifying installation and performance, and preparing a commissioning report12 References: 1: LEED v4 Reference Guide for Building Design and Construction, Energy and Atmosphere Prerequisite: Fundamental Commissioning and Verification, page 562. 2: LEED v4 Reference Guide for Building Design and Construction, Glossary, page 1020.


NEW QUESTION # 24
The LEED project has a main entrance and two service entrances in an alley behind the building. Which entrances need non-smoking signage and at what maximum distance from the door(s) can the non-smoking signage be posted?

  • A. At the main entrance, 10 ft. (3 m) from the door
  • B. At the main entrance and the two service entrances, 10 ft. (3 m) from the doors
  • C. At the main entrance, 25 ft. (7.5 m) from the door
  • D. At the main entrance and the two service entrances, 25 ft. (7.5 m) from the doors

Answer: B

Explanation:
Explanation
According to the LEED v4 Reference Guide for Building Design and Construction, no smoking signage must be placed within 10 feet (3 meters) of every building entrance, except for alarmed emergency exits. This applies to both the main entrance and the service entrances, regardless of their location or frequency of use.The signage is intended to communicate the no-smoking policy to occupants and visitors and prevent environmental tobacco smoke from entering the building.References: EQ Prerequisite Environmental Tobacco Smoke Control, LEED v4 Reference Guide for Building Design and Construction123


NEW QUESTION # 25
A decorative overhead light fixture is specified for a project that costs $1,500 USD and uses recycled water bottles as part of the diffuser shade. The shades are 10% of the overall weight of the fixture and are 50% post-consumer recycled content. Assuming no other portions of the fixture meet sustainability criteria, what would the contributing value of the fixture be?

  • A. $1,500
  • B. $750
  • C. $150
  • D. $75

Answer: D

Explanation:
Explanation
This option requires the project to calculate the contributing value of the fixture by multiplying the cost of the fixture by the percentage of recycled content by weight1. Since the shades are 10% of the overall weight of the fixture and are 50% post-consumer recycled content, the contributing value of the fixture is:
$1,500 x 10% x 50% = $75
References: = LEED v4: Building Design + Construction Guide, Recycled content | U.S. Green Building Council.


NEW QUESTION # 26
A newly constructed school has installed solar thermal systems and wind turbines on site. To achieve the maximum number of Energy and Atmosphere points, which team members must be included?

  • A. Energy Modeler and Contractor
  • B. Energy Modeler and Commissioning (Cx) Agent
  • C. Commissioning (Cx) Agent and Facilities Manager
  • D. Construction Manager and Energy Modeler

Answer: B

Explanation:
Explanation
To achieve the maximum number of Energy and Atmosphere points, the project team must include an energy modeler and a commissioning agent.The energy modeler is responsible for performing the whole-building energy simulation that demonstrates the energy performance improvement over the baseline building, which is required for Energy and Atmosphere Prerequisite 2 and Credit 11.The commissioning agent is responsible for verifying that the building's energy systems are installed, calibrated, and perform according to the owner's project requirements, basis of design, and construction documents, which is required for Energy and Atmosphere Prerequisite 1 and Credit 31.The commissioning agent also ensures that the renewable energy systems are properly integrated and functioning2. The contractor and the construction manager are not directly involved in the energy modeling or commissioning process, although they must follow the design specifications and coordinate with the commissioning agent. The facilities manager is not required for achieving the Energy and Atmosphere points, although they may benefit from the training and documentation provided by the commissioning agent.References:
* LEED v4 for Building Design and Construction, p.361
* Understanding Integrative Design in LEED v4, p.92


NEW QUESTION # 27
When the LEED AP is applying the Integrative Process to a Building Design and Construction project, which of the following information is required to be present in the Owner's Project Requirements (OPR)?

  • A. All applicable codes and standards
  • B. Interior finishes related to the project
  • C. All project team members and applicable roles
  • D. Energy efficiency goals and training requirements

Answer: D

Explanation:
Explanation
Energy efficiency goals and training requirements are required to be present in the Owner's Project Requirements (OPR) when applying the Integrative Process to a Building Design and Construction project.
According to the LEED v4 BD+C Reference Guide, the OPR is a document that details the ideas, concepts, and criteria that are determined by the owner to be important to the success of the project 1. The OPR must include, among other things, the following information related to energy efficiency 1:
The owner's energy performance goals and expectations
The owner's requirements for energy metering and monitoring
The owner's requirements for energy modeling and analysis
The owner's requirements for commissioning and verification
The owner's requirements for training and documentation
The other options are not required to be present in the OPR, as they are either related to other aspects of the project, such as codes and standards, interior finishes, or project team members, or they are not relevant to the Integrative Process, which focuses on early analysis of energy, water, and site systems 2.References: LEED v4 BD+C Reference Guide, Integrative Process Category, IPc Integrative Process, page 632.


NEW QUESTION # 28
What stage of LEED for Neighborhood Development certification listed below is eligible for points under Building Design and Construction: New Construction, Location and Transportation Credit, LEED for Neighborhood Development Location?

  • A. LEED for Neighborhood Development Pilot, Stage 3 LEED for Neighborhood Development Certified Project
  • B. LEED for Neighborhood Development Pilot, Stage 1 LEED for Neighborhood Development Pre-reviewed Plan
  • C. LEED 2009, Stage 1 Conditional Approval of LEED for Neighborhood Development Plan
  • D. LEED v4, LEED for Neighborhood Development Conditional Approval

Answer: A

Explanation:
Explanation
The only stage of LEED for Neighborhood Development certification that is eligible for points under Building Design and Construction: New Construction, Location and Transportation Credit, LEED for Neighborhood Development Location, is LEED for Neighborhood Development Pilot, Stage 3 LEED for Neighborhood Development Certified Project.This is because the credit requires that the project be located within the boundary of a development that has achieved certification under LEED for Neighborhood Development (either Stage 2 or Stage 3 under the Pilot or 2009 rating systems, or Certified Plan or Certified Project under the LEED v4 rating system)1The other stages listed in the question are either conditional approvals or pre-reviews that do not guarantee certification23References:1: LEED v4 Reference Guide for Building Design and Construction, Location and Transportation Credit: LEED for Neighborhood Development Location, page
460.2: LEED for Neighborhood Development Location - Above Green33: LEED v4: Building Design + Construction Guide - U.S.Green Building Council1


NEW QUESTION # 29
What is the minimum number of members of the integrated project team for the Integrative Process Prerequisite, Integrative Project Planning and Design?

  • A. Two
  • B. Six
  • C. One
  • D. Four

Answer: B


NEW QUESTION # 30
When the project occupancy is not known, which method is recommended?

  • A. Default occupant density from ASHRAE 62.1-2010, Table 6-1
  • B. Default occupant density from ASHRAE 90.1-2010, Table G3.1.1A
  • C. Occupancy measured for eight hours, between 8 a.m. and 5 p.m., for all occupancy patterns
  • D. Weekly average taken into account all the occupants in a typical 24-hour day of operation

Answer: A

Explanation:
Explanation
This method is recommended when the project occupancy is not known, because it provides the default occupant density values for various space types, such as offices, classrooms, retail, and restaurants1. These values are based on the typical or average occupancy of similar spaces, and can be used to estimate the ventilation requirements and energy performance of the project2.
References: = LEED v4: Building Design + Construction Guide, ASHRAE 62.1-2010, Table 6-1.


NEW QUESTION # 31
Location and Transportation Credit, Reduced Parking Footprint calculations must include

  • A. parking outside the project boundary but used by the project
  • B. parking within 1/4 mi. (0.40 km) radius of the project boundary
  • C. motorbike spaces
  • D. on-street parking in public rights-of-way

Answer: A

Explanation:
Explanation
This option requires the project to include all parking spaces that are outside the project boundary but are used by the project occupants, visitors, or customers in the calculations for the reduced parking footprint credit1.
This option ensures that the project accounts for the total parking demand and supply associated with the project, regardless of the location of the parking spaces2.
References: = [LEED v4: Building Design + Construction Guide], NC-v4 LTc7: Reduced parking footprint | LEEDuser.


NEW QUESTION # 32
When working on a renovation project, asbestos containing materials have been found on the perimeter walls.
When calculating the percentage of building being reused under the Materials and Resources Credit, Building Life-Cycle Impact Reduction, the materials remediated will be

  • A. excluded if the total volume is less than 25% of the building being reused
  • B. excluded from the calculation
  • C. excluded if the total volume is more than 25% of the building being reused
  • D. included in the calculation

Answer: B

Explanation:
Explanation
The Materials and Resources Credit, Building Life-Cycle Impact Reduction, rewards projects that reuse existing building structures and envelopes, or salvage materials from off-site or on-site sources. According to the LEED v4 Reference Guide for Building Design and Construction, the project team must calculate the percentage of building being reused by dividing the area of the existing building structure and envelope that is reused by the total area of the completed building structure and envelope1. However, the project team must exclude from the calculation any hazardous materials that are remediated as a part of the project, such as asbestos, lead, mold, or PCBs1. Therefore, the asbestos containing materials found on the perimeter walls will be excluded from the calculation, regardless of the volume.
References:
*LEED v4 Reference Guide for Building Design and Construction, Materials and Resources Credit: Building Life-Cycle Impact Reduction, page 5451
*Building life-cycle impact reduction | U.S. Green Building Council2


NEW QUESTION # 33
A new commercial building is being designed to use small capacity air handling units. To meet the requirements of the Carbon Dioxide Monitoring strategy in the Indoor Environmental Quality Credit, Enhanced Indoor Environmental Quality Strategies, where would CO2 monitors need to be located?

  • A. In each occupied space over 500 ft2 (46 m2)
  • B. In each occupied space
  • C. In each densely occupied space
  • D. In each occupied space and outdoors

Answer: C

Explanation:
Explanation
According to the LEED v4 Reference Guide for Building Design and Construction, the Carbon Dioxide Monitoring strategy requires CO2 monitors to be located in each densely occupied space, which is defined as a space with a design occupant density of 25 people or more per 1,000 square feet (93 square meters). This strategy is intended to provide feedback on ventilation system performance and indoor air quality12 References: 1: LEED v4 Reference Guide for Building Design and Construction, Indoor Environmental Quality Credit: Enhanced Indoor Air Quality Strategies, Option 2: Additional Enhanced IAQ Strategies, Strategy 3: Carbon Dioxide Monitoring, page 704. 2: LEED v4 Reference Guide for Building Design and Construction, Glossary, page 1019.


NEW QUESTION # 34
For Location and Transportation Credit, Access to Quality Transit, a project team preparing timetables and service-level documentation must ensure the materials include

  • A. verification that a weighted daily average has been used for each qualifying route
  • B. confirmation that each qualifying route features paired route service (service in opposite directions)
  • C. confirmation that functional entries of the project are within 3/4 mi. (1.20 km) of the stop
  • D. verification that a weighted building average has been used for each qualifying functional entry

Answer: A

Explanation:
Explanation
This option requires the project team to calculate the weighted daily average of the number of trips per day for each qualifying route, using the formula provided in the LEED v4: Building Design + Construction Guide.
This option ensures that the transit service frequency is accurately represented and meets the minimum thresholds for weekday and weekend trips, as shown in Table 1 and Table 2 of the guide.
References: = [LEED v4: Building Design + Construction Guide], Access to Quality Transit.


NEW QUESTION # 35
Which of the following must be included in the Sustainable Sites Credit, Site Assessment?

  • A. A targeted Brownfield remedy plan
  • B. Historic preservation plan to include neighboring properties
  • C. Proximity of vulnerable populations to major sources of air pollution
  • D. The surrounding density within a 1/4 mi. (0.40 km) radius of the project boundary

Answer: C

Explanation:
Explanation
The correct answer is C. Proximity of vulnerable populations to major sources of air pollution.
According to the LEED v4.1 Reference Guide for Building Design and Construction, the Site Assessment credit requires projects to conduct and document a site inventory and analysis that covers the following topics1:
Topography
Hydrology
Climate
Vegetation
Soils
Human use
Human health effects
The human health effects topic includes identifying the proximity of vulnerable populations, such as children, elderly, or low-income residents, to major sources of air pollution, such as highways, power plants, or industrial facilities. This information can help the project team design strategies to minimize the exposure of occupants and visitors to harmful pollutants and improve the indoor and outdoor air quality of the project1.
The other options are not required for the Site Assessment credit, although they may be relevant for other credits or prerequisites. A targeted Brownfield remedy plan is required for the Brownfields Remediation credit, which applies to projects located on sites contaminated by past uses1. A historic preservation plan to include neighboring properties is not required for any LEED credit, although projects that involve historic buildings or districts must comply with local regulations and standards for preservation1. The surrounding density within a 1/4 mi. (0.40 km) radius of the project boundary is not required for the Site Assessment credit, but it is used to calculate the points for the Surrounding Density and Diverse Uses credit, which encourages projects to locate in areas with high levels of existing development and mixed land uses1.


NEW QUESTION # 36
......

Dumps Real USGBC LEED-AP-BD-C Exam Questions [Updated 2024]: https://www.pass4sures.top/USGBC-LEED/LEED-AP-BD-C-testking-braindumps.html

Free LEED-AP-BD-C Exam Dumps to Pass Exam Easily: https://drive.google.com/open?id=1wTizDOKD6UizZonUfOFZOS7XRN0EzGQU