The AACE-PSP certification exam covers a wide range of topics, including project planning, scheduling, risk management, earned value management, and cost control. It is designed for professionals who have experience in project planning and scheduling and are looking to advance their career by demonstrating their expertise in the field. AACE-PSP exam is challenging and requires a deep understanding of project management principles and techniques. However, passing the AACE-PSP certification exam can provide significant benefits, including increased job opportunities, higher salaries, and greater credibility with clients and colleagues.
NEW QUESTION # 20
Activity C is a
- A. Continuous activity.
- B. 1-day activity.
- C. Contentious activity.
- D. Milestone.
Answer: D
NEW QUESTION # 21
Theoretically construct a summary activity for activities 6001 through 6003. Identify the governing predecessor and successor activities for the hammock:
- A. Predecessor is activity 9001, successor is activity 9002
- B. Predecessor is activity 5001, successor is activity 8001
- C. Predecessor is activity 4001, successor is activity 8001
- D. Predecessor is activity 5001, successor is activity 8002
Answer: B
NEW QUESTION # 22
In the "normal" schedule, excluding Activity 1000, what activity(s) are concurrent with Activity 3001?
- A. 2004.
- B. 2003 and 7001.
- C. 4001 and 5001.
- D. 4001, 5001 and 6001.
Answer: C
NEW QUESTION # 23
Assuming a total of 30 lifts per crane per day, what is the maximum number of lifts that could be accomplished using 3 small tower cranes over a 5-day period?
- A. 450 lifts
- B. 300 lifts
- C. 45 lifts
- D. 150 lifts
Answer: A
NEW QUESTION # 24
If a cost estimate assumes that 240 hours will be expended on a given activity, and the projected crew size expected to perform that activity is 5 personnel working and 8-hour workday, what is the calculated duration for the activity?
- A. 5 days
- B. 8 days
- C. 4 days
- D. 6 days
Answer: D
NEW QUESTION # 25
What method offers the best chance of the schedule being used effectively to implement the project in the field?
- A. Allow large time contingencies on milestones and completion deadlines.
- B. Obtain consent and agreement to the schedule from the key project personnel.
- C. Issue detailed schedule updates as frequently as possible.
- D. Include detailed and stringent set of scheduling specifications in the contract.
Answer: B
NEW QUESTION # 26
Based on the stated costs, what percentage of the total cost comes from the 2000 series of activities?
- A. 2.3% (1 : 43.501).
- B. 8.6% (1 : 11.591)
- C. 9.1% (1 : 11.000).
- D. 3.9% (1 : 25.708)
Answer: A
NEW QUESTION # 27
Which is NOT an industry-recognized methodology for quantifying critical delay?
- A. Gantt Chart.
- B. Time Impact.
- C. Collapsed As-Built.
- D. Periodic Windows.
Answer: A
NEW QUESTION # 28
Using the "normal" schedule, and assuming you are billing on the last day of the month for previous month and for appropriate partial months, how many invoices will you have for this project?
- A. 36.
- B. 42.
- C. 37.
- D. 40.
Answer: A
NEW QUESTION # 29
Using the "normal" schedule, if you start Activity 7001 on April 1, 2002, and using a 5-day workweek, what the finish date for Activity 7001?
- A. 06-18-02.
- B. 06-05-02.
- C. 06-04-02.
- D. 06-11-02.
Answer: B
NEW QUESTION # 30
What problems can a soils engineer deal with on a project?
- A. Survey error.
- B. Hidden subsurface conditions.
- C. Archeological findings.
- D. Toxic soils.
Answer: B
NEW QUESTION # 31
There is only enough room for a maximum of 4 cranes to be placed on-site. Assuming that a single crane can perform 35 lifts per day and that a column pour requires 60 lifts, what is the minimum number of tower cranes that should be used for the above described column pours?
- A. 4 cranes
- B. 2 cranes
- C. 1 crane
- D. 3 cranes
Answer: B
NEW QUESTION # 32
Which of the following will always describe the critical path? The path with
- A. Zero float.
- B. The longest duration through the network.
- C. The shortest duration and negative float.
- D. Negative float.
Answer: A
NEW QUESTION # 33
Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?
- A. 407 days
- B. 255 days
- C. 267 days
- D. 362 days
Answer: A
NEW QUESTION # 34
What is the workweek period for this project?
- A. Sunday through Saturday
- B. Monday through Saturday
- C. Sunday through Friday
- D. Monday through Friday
Answer: A
NEW QUESTION # 35
Which of the following documents is most likely to be of the LEAST value to a planner/scheduler when planning a contractor's baseline critical path schedule for the construction of a large high-clearance bridge located very near an airport? The contractor has been awarded the contract.
- A. The project plans and specifications
- B. The government's report on future high-clearance bridge projects
- C. The project geotechnical report
- D. The regulations published by the government aviation agency
Answer: B
NEW QUESTION # 36
By subtracting a measured unit productivity rate during an impacted period from the unit productivity rate during an unimpacted period, the resulting value represents:
- A. Productivity efficiency.
- B. Acceleration.
- C. Productivity loss.
- D. Production output.
Answer: C
NEW QUESTION # 37
As a change to the network for the current update, activity 6002 is required to begin ten days after the beginning of activity 6001. Which is the simplest logic organization?
- A. A finish-to-start relationship with a ten-day lag assigned to activity 6002; activity 6001 will be dependent on activity 6002
- B. A start-to-finish relationship with both activities 6001 and 6002 having a ten-day lag
- C. A start-to-start relationship with a ten-day lag assigned to activity 6001; activity 6002 will be dependent on activity 6001
- D. A start-to-start to relationship for both activities 6001 and 6002 with a ten-day lag assigned to activity
6002.
Answer: A
NEW QUESTION # 38
You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?
- A. Not suitable for complicated projects with multiple planned critical paths.
- B. Not suitable for projects with long durations.
- C. Less accurate as the analysis advances through the project.
- D. Accuracy is increased by inserting delaying events into the as-planned schedule.
Answer: D
NEW QUESTION # 39
All the following describe the critical path of a schedule EXCEPT:
- A. Changed by redefining the network logic or changing activity durations or both.
- B. Frequently defined as the shortest path through the schedule.
- C. The series of activities having the least amount of total float.
- D. Determined by network logic and is the chain of activities that controls the overall project completion time.
Answer: B
NEW QUESTION # 40
Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?
- A. Front end loading.
- B. Start and finish constraints.
- C. Preferential logic.
- D. Multiple calendars.
Answer: A
NEW QUESTION # 41
Which of the following project planning situations is the most frequent contributor to cost overruns?
- A. Inadequate definition of scope at the estimate (budget) stage
- B. Insufficient planning for change management
- C. Inappropriate definition of work breakdown structure
- D. lack of detailed planning for operational start-up
Answer: A
NEW QUESTION # 42
Constraints control events or activities that __________________.
- A. May be over-ridden by activity logic.
- B. Are not based on project relationships.
- C. Affect only the backward pass.
- D. Affect only the forward pass.
Answer: A
NEW QUESTION # 43
......
The AACE-PSP Certification is designed for individuals who specialize in planning, scheduling, and project management. Planning & Scheduling Professional (PSP) Exam certification program is ideal for professionals seeking to enhance their skills in project planning and scheduling, Cost management, Risk Management, Effective communication, and other related fields. The AACE-PSP Certification program aims to educate individuals about fundamental project management concepts and practices that will help them excel in their professional careers.
AACE-PSP Exam Dumps - PDF Questions and Testing Engine: https://www.pass4sures.top/AACE-Certification/AACE-PSP-testking-braindumps.html
Latest AACE-PSP Exam Dumps for Pass Guaranteed: https://drive.google.com/open?id=1TYfm65rY73DEVO4tL442QMj3jvdXgjfc