NEW QUESTION 13
Which of the following processes lead to an entry in the MRP planning file? Note: There are 3 correct answers to this question.
- A. Change of the storage bin
- B. Creation of a purchasing contract
- C. Change of the material's procurement type
- D. Creation of a sales order
- E. Creation of dependent requirements
Answer: C,D,E
NEW QUESTION 14
On which of the following levels can you influence the availability check for the components of production orders?
There are 2 correct answers to this question.
Response:
- A. Production controller
- B. Material master
- C. MRP controller
- D. Production order type
Answer: B,C
NEW QUESTION 15
What is the purpose of collective orders?
- A. To combine order management of co-products and by-products with the main product
- B. To manage production orders for an entire finished product on multiple levels
- C. To post production costs on a cost collector instead of the production order
- D. To post any component withdrawals single back flush with order confirmation
Answer: B
NEW QUESTION 16
Which chart types does the tabular planning table provide in SAP S/4HANA? Note: There are 2 correct answers to this question.
- A. Work center capacities chart
- B. Orders (dispatched) chart
- C. Order (pool) chart
- D. Capacity requirements chart
Answer: A,D
NEW QUESTION 17
What is SAP's strategic solution to perform Sales and Operations planning when you use SAP S/4HANA Manufacturing?
Please choose the correct answer.
Response:
- A. Integrated Business Planning
- B. PP Standard Sales and Operations Planning
- C. APO Demand Planning
- D. Flexible Planning
Answer: A
NEW QUESTION 18
What must be used in the system to plan the requirements for different subcontractors separately?
Response:
- A. Storage locations
- B. MRP areas
- C. Production versions
- D. Planning plant
Answer: B
NEW QUESTION 19
Which bill of material (BOM) categories can you define in SAP S/4HANA? Note: There are 2 correct answers to this question.
- A. Functional Location BOM
- B. Class BOM
- C. Work Center BOM
- D. Sales Order BOM
Answer: A,D
NEW QUESTION 20
Which of the following objects can you release so that the business transactions for process order execution and process management can be executed?
There are 2 correct answers to this question.
Response:
- A. Individual operations
- B. Individual phases
- C. Individual control recipes
- D. Individual process instructions
Answer: A,B
NEW QUESTION 21
The production plan is being disrupted by last minute demands that are entered in the system. Which is the most efficient way to handle last minute demands and protect the current production plan?
There are 2 correct answers to this question.
Response:
- A. In the material master record, set MRP type to P4 and a planning time fence on the replenishment lead time of the material
- B. Manually firm all planned orders for materials within the replenishment lead time of the material
- C. In the stock requirements list, set a manual firming fence for a date based on the replenishment lead time of the material
- D. In the material master record, set MRP type to P1 and a planning time fence on the replenishment lead time of the material
Answer: C,D
NEW QUESTION 22
Which Kanban master data object controls the relationship between the supply and demand source?
Please choose the correct answer.
Response:
- A. Rate routing
- B. Kanban container
- C. Control cycle
- D. Production supply area
Answer: C
NEW QUESTION 23
You want to procure your material components based on a forecast for the finished material derived from historical sales. When customers order, you produce the finished product and reserve it for that particular order.
Which is the appropriate planning strategy to use?
Please choose the correct answer.
Response:
- A. Production by lot size (30)
- B. Planning with final assembly (40)
- C. Make-to-order production (20)
- D. Planning without final assembly (50)
Answer: D
NEW QUESTION 24
What capabilities does SAP S/4HANA embedded analytics provide?
There are 2 correct answers to this question.
Response:
- A. Strategic analysis
- B. Automatic update of story boards
- C. Real time decision support
- D. Comparison of current data with historical data to identify trends
Answer: A,C
NEW QUESTION 25
During production order creation, several valid production versions are found. How does the system choose the product conversion?
- A. Lot size or material cost
- B. Validity period or sales order
- C. Planned order or material number
- D. Alphanumeric or quota arrangement
Answer: D
NEW QUESTION 26
How can you avoid order proposals for planned independent requirements with dates in the past?
There are 2 correct answers to this question.
Response:
- A. Set the requirements reduction indicator in the requirements class
- B. Maintain adjustment parameter in the MRP group
- C. Reorganize planned independent requirements
- D. Use a planning strategy with requirements consumption
Answer: B,C
NEW QUESTION 27
In Make-to-order production, which field controls whether the components will be planned as sales order specific stock?
Please choose the correct answer.
Response:
- A. The Planning Strategy of the finished product
- B. The item category of the component in the BOM
- C. The Individual/Collective indicator of the component
- D. The MRP Type of the component
Answer: A
NEW QUESTION 28
What is the difference between co-products and by-products?
- A. Only by-products have a zero inventory valuation.
- B. Only co-products can be manufactured in isolation from the main product.
- C. Only co-products are identified by a special item category in the bill of material (BOM).
- D. Only co-products appear in the process or production order settlement rule.
Answer: D
NEW QUESTION 29
What are some of the advantages of using Kanban?
There are 2 correct answers to this question.
Response:
- A. It is a simplified form of production control
- B. Replenishments are based on centralized planning
- C. Replenishments are created close to the actual need
- D. It is mostly accomplished by manual postings
Answer: A,C
NEW QUESTION 30
Your customer wants to include restricted-use stock as a potential receipt in the existing ATP check for component availability.
Which information is required to implement this change request in the scope of check?
There are 2 correct answers to this question.
Response:
- A. The checking group from the material master
- B. The checking control for the order type
- C. The ATP category for restricted-use stock
- D. The checking rule from the business application
Answer: A,D
NEW QUESTION 31
Which warehouse management functions are available in SAP EWM but NOT in SAP WM?
There are 3 correct answers to this question.
Response:
- A. Handling Unit Management
- B. Labor Management
- C. Expected goods receipt
- D. Slotting
- E. Yard Management
Answer: B,C,D
NEW QUESTION 32
Which reports can you access via the order and resource reporting transaction in advanced planning?
There are 3 correct answers to this question.
Response:
- A. Production overview
- B. Operation list
- C. Production list
- D. Planning file entries
- E. WIP list
Answer: A,B,E
NEW QUESTION 33
Where does the system check master data selection settings during the creation of planned orders and production orders? Note: There are 3 correct answers to this question.
- A. In the MRP controller
- B. In the routing
- C. In the production version
- D. In the production order type
- E. In the bill of materials (BOM)
Answer: A,B,D
NEW QUESTION 34
Which SAP solutions can be used for forecast ng in Supply Chain Planning? Note: There are 2 correct answers to this question.
- A. Material Requirements Planning (MRP)
- B. Supply Chain Management (SCM)
- C. Capacity Requirements Planning (CRP)
- D. Integrated Business Planning (IBP)
Answer: B,D
NEW QUESTION 35
Which of the following are capabilities of multidimensional reporting in SAP S/4HANA embedded analytics?
There are 3 correct answers to this question.
Response:
- A. Scheduling
- B. Sort
- C. Filters
- D. Forecast
- E. Drilldown
Answer: B,C,E
NEW QUESTION 36
You have a scheduling agreement with a vendor. You want classic MRP to automatically create schedule lines in case of material shortage. What must you do? Note: There are 2 correct answers to this question.
- A. Set the creation indicator for purchase requisitions on the initial screen of the MRP run.
- B. Set the creation indicator for delivery schedule lines on the initial screen of the MRP run.
- C. Add the agreement to the quota arrangement and mark it for MRP relevance.
- D. Add the agreement to the source list and mark it for MRP relevance.
Answer: B,D
NEW QUESTION 37
Which functional capabilities does the Detailed Scheduling Board have?
There are 2 correct answers to this question.
Response:
- A. Change planned order quantities
- B. Undo for drag & Drop planning activities
- C. Enter time-ticket confirmation for production orders
- D. Change sales order quantities
Answer: A,B
NEW QUESTION 38
......