NEW QUESTION 30
What is described as an organization's unique attitude towards risk taking

  • A. Risk management
  • B. Risk evaluation
  • C. Risk appetite
  • D. Risk tolerance

Answer: C

 

NEW QUESTION 31
Which is a key decision made during the 'directing a project' process?

  • A. Approve the project manager role description
  • B. Approve the proposed project mandate
  • C. Confirm that the benefits management approach addresses all expected benefits
  • D. Select and appoint the project executive

Answer: A

Explanation:
Section: Volume B
Explanation/Reference:
Reference https://www.greycampus.com/opencampus/prince-2-practitioner/purpose-of-directing-a-project- process-in-prince2

 

NEW QUESTION 32
Which is a benefit of using PRINCE2?

  • A. Can be tailored by leaving out elements of the method for some projects
  • B. Can be applied to any type of project
  • C. Enables the management of projects as well as of 'business as usual' activities
  • D. Avoids the need to involve corporate or programme management

Answer: B

Explanation:
Section: Volume A

 

NEW QUESTION 33
Which product identifies the management stages and timescales of a project?

  • A. Project Product Description
  • B. Project Brief
  • C. Project Plan
  • D. Initiation Stage Plan

Answer: C

 

NEW QUESTION 34
Which describes the 'Identify Risks' step within the recommended risk management procedure?

  • A. Gather information about the project environment and objectives
  • B. Identify responses to risks documented in the Business Case
  • C. Identify uncertainties that may impact on the delivery of the project objectives
  • D. Identify the roles to be involved in risk management activities

Answer: C

 

NEW QUESTION 35
Which is a purpose of the Controlling a Stage process?

  • A. Provide a fixed reference point at which acceptance for the project product is confirmed
  • B. Enable the organization to understand the work that needs to be done to deliver the project's products
  • C. Enable the Project Board to be provided with sufficient information to authorize the next stage
  • D. Assign work to be done and take corrective action to ensure that the stage remains within tolerance

Answer: D

Explanation:
Section: Volume A

 

NEW QUESTION 36
Which is a typical core activity within configuration management?

  • A. Status accounting
  • B. Communication
  • C. Assessment
  • D. Quality control

Answer: A

 

NEW QUESTION 37
Which statement is FALSE?

  • A. A project benefit is only realized after the project has closed
  • B. A project outcome perceived to be negative by one or more stakeholders is a dis-benefit
  • C. A project outcome is the result of the change derived from using the project's outputs
  • D. A project's output is any of the project's specialist products

Answer: A

 

NEW QUESTION 38
Which should be provided by corporate or programme management before the Starting up a Project process commences?

  • A. Sufficient information to identify the prospective Executive
  • B. Authority to initiate a project
  • C. The Project Initiation Documentation
  • D. A Project Brief

Answer: A

Explanation:
Section: Volume B

 

NEW QUESTION 39
Which is a purpose of the 'closing a project' process?

  • A. To provide the project board with information to judge the success of a stage
  • B. To confirm the project has nothing more to deliver
  • C. To establish mechanisms for forecasting project objectives
  • D. To establish mechanisms to judge whether the project is still viable

Answer: B

Explanation:
Explanation
Reference http://prince2.wiki/Closing_a_Project#Objective

 

NEW QUESTION 40
Which is a purpose of the quality theme?

  • A. To establish baselines against which any changes to products can be assessed
  • B. To establish how the project will ensure that all products created meet their requirements
  • C. To identify all the products of the project to ensure the scope has been adequately defined
  • D. To determine the communication needs of the organization's quality assurance function

Answer: B

 

NEW QUESTION 41
Which is a minimum requirement for applying the risk theme?

  • A. Threats must be assessed for their impact on the viability of the project
  • B. The PRINCE2 risk management procedure must be followed
  • C. Team managers must maintain their own risk registers
  • D. A single role that is responsible for all risks must be defined

Answer: A

Explanation:
Explanation
Reference https://www.prince2primer.com/prince2-2017-risk-theme-changes/

 

NEW QUESTION 42
Which is a purpose of the Controlling a Stage process?

  • A. Provide a fixed reference point at which acceptance for the project product is confirmed
  • B. Enable the organization to understand the work that needs to be done to deliver the project's products
  • C. Enable the Project Board to be provided with sufficient information to authorize the next stage
  • D. Assign work to be done and take corrective action to ensure that the stage remains within tolerance

Answer: D

 

NEW QUESTION 43
What is the collective name for individuals or groups who may be affected by a project?

  • A. Team members
  • B. Customers
  • C. Stakeholders
  • D. Project Support

Answer: C

 

NEW QUESTION 44
Which is one of the six aspects of project performance that needs to be managed?

  • A. Risk
  • B. Security
  • C. Progress
  • D. Change

Answer: A

 

NEW QUESTION 45
Which is a key decision made during the 'directing a project' process?

  • A. Approve the project manager role description
  • B. Approve the proposed project mandate
  • C. Confirm that the benefits management approach addresses all expected benefits
  • D. Select and appoint the project executive

Answer: A

Explanation:
Explanation
Reference
https://www.greycampus.com/opencampus/prince-2-practitioner/purpose-of-directing-a-project-process-in-princ

 

NEW QUESTION 46
Which is part of quality control?

  • A. Produce quality records to show that the planned quality activities have been carried out
  • B. Define the quality responsibilities of those involved in the production of the products
  • C. Maintain the corporate organization's quality management system
  • D. Document the project's acceptance criteria in the Project Product Description

Answer: A

 

NEW QUESTION 47
Which is an objective of the Starting up a Project process?

  • A. Agree how the project will be monitored and controlled after initiation
  • B. Authorize the Project Manager to proceed with the initiation stage
  • C. Identify who will be responsible for creating the Project Plan
  • D. Agree how issues and changes will be identified, assessed and controlled

Answer: C

 

NEW QUESTION 48
Which should be funded by a change budget?

  • A. Initiation stage
  • B. Handover activities
  • C. Change Authority
  • D. Increase in agreed scope

Answer: D

 

NEW QUESTION 49
Which is a purpose of the 'initiating a project' process?

  • A. To identify the number of work packages required
  • B. To establish solid foundations for a project
  • C. To decide if it is worthwhile to initiate a project
  • D. To decide on the project approach

Answer: B

Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Initiating_a_Project#Objective

 

NEW QUESTION 50
Which is an objective of the Starting up a Project process?

  • A. Confirm that there is a validmethod in place to measure the expected project benefits
  • B. Approve allProduct Descriptions prior to project initiation
  • C. Prevent projects with unrealistic delivery dates from being initiated
  • D. Obtain approval from corporate or programme management for the Communication
    Management Strategy

Answer: C

 

NEW QUESTION 51
......

Prepare for your PRINCE2 certification with the updated Pass4sures PRINCE2Foundation exam questions: https://drive.google.com/open?id=1Gg2VzsD0pLJfyRcj1NYNorbP-8VRcBSP

Get Latest PRINCE2Foundation Dumps Exam Questions in here: https://www.pass4sures.top/PRINCE2-Certification/PRINCE2Foundation-testking-braindumps.html