NEW QUESTION 140
Which of the following is a model used for monitoring reliability growth?
Response:

  • A. Arrehenius
  • B. Duane
  • C. Lognormal
  • D. Normal

Answer: B

 

NEW QUESTION 141
A company has produced a new module. The failure data on 40 returns are shown below.

Which of the following is the first step in the review of this situation ?
Response:

  • A. Identify the field service personnel who handled the returns.
  • B. Find the median of the data set.
  • C. Determine the location in which the failure occurred.
  • D. Categorize the data by using a Pareto analysis.

Answer: C

 

NEW QUESTION 142
For a reliability plan to be most effective, the reliability tasks should be integrated with which of the following plan?
Response:

  • A. Product design and development.
  • B. Product sales.
  • C. Reliability centered maintenance.
  • D. Product distribution

Answer: A

 

NEW QUESTION 143
The following fault tree diagram was developed by a team.

The probability are as follow:
A1 = 0.90 B1 = 0.90 C1 = 0.80
A2 = 0.80 B3 = 0.80 C2 = 0.70
A4 = 0.70
The likelihood that the system fault will occur is
Response:

  • A. 0.5034
  • B. 0.4977
  • C. 0.3073
  • D. 0.3686

Answer: B

 

NEW QUESTION 144
A company has produced a new module. The failure data on 40 returns are shown below.

If the time to failure follows a normal distribution, what is the probability that time to failure exceeds 20 hours ?
Response:

  • A. 0.972
  • B. 0.950
  • C. 0.050
  • D. 0.028

Answer: D

 

NEW QUESTION 145
Measures of availability include:
I. Effectiveness.
II. Inherent.
III. Achieved.
IV. Dependability.
V. Capability.
Response:

  • A. I, III and IV
  • B. II and III only
  • C. III, IV and V
  • D. II, III and IV

Answer: B

 

NEW QUESTION 146
What is the MOST vital information to know about a system in order to perform a hardware FMECA?
Response:

  • A. Full process information.
  • B. The details of the system.
  • C. The details of the system.
  • D. The details of the subsystems.

Answer: C

 

NEW QUESTION 147
A system is turned off every 30 days for 5 minutes for on line maintenance. If the probability of system failure due to hardware failure is negligible, what is the system's unavailability?
Response:

  • A. 0.0333
  • B. 1.157 × 10 -4
  • C. 3.472 × 10 -4
  • D. 0.999

Answer: B

 

NEW QUESTION 148
Which of the following techniques is MOST beneficial in tracking a process to determine whether corrective action should be taken?
Response:

  • A. Pareto analysis.
  • B. Control charting.
  • C. Time series plotting.
  • D. Trend analysis.

Answer: B

 

NEW QUESTION 149
Random sampling plans are based on which of the following assumption?
Response:

  • A. Every item has an equal chance of being selected.
  • B. A specific dependency model has been selected.
  • C. The process is unstable.
  • D. The data are accurate.

Answer: A

 

NEW QUESTION 150
A go/no-go device is tested until it fails. If X is the number of tests to first failure with no wear out present, and the probability of success on each test is .99, then the probability that X is greater than 5 is:
Response:

  • A. 0.9510
  • B. 0.9610
  • C. 0.9410
  • D. 0.9310

Answer: A

 

NEW QUESTION 151
For equal length missions an increase in the MTBF will yield:
I. An increase in availability.
II. An increase in reliability.
III. A decrease in reliability.
IV. A decrease in availability.
Response:

  • A. III
  • B. I
  • C. I and II
  • D. III and IV

Answer: C

 

NEW QUESTION 152
The two principal measures of failure during risk assessment are which of the following?
Response:

  • A. Failure analysis and failure effects.
  • B. Failure mode and failure mechanism.
  • C. Failure severity and failure probability.
  • D. Failure method and failure mode.

Answer: C

 

NEW QUESTION 153
An air handling system has a MTBF of 8000 hours, MTBMct of 120 hours, and MMT (mean maintenance action time) of 230 hours. Determine the potential availability.
Response:

  • A. 0.9852.
  • B. 0.9721.
  • C. 0.9866.
  • D. 0.9575.

Answer: A

 

NEW QUESTION 154
Reliability prediction is:
Response:

  • A. A popular method as simulation theory.
  • B. A continuous process starting with paper predictions.
  • C. More important than reliability attained in the field.
  • D. A one time estimation process.

Answer: B

 

NEW QUESTION 155
Which of the following statements is TRUE about probability distributions?
Response:

  • A. The variance is used to measure the central tendency
  • B. The 3rd moment about the mean is used to measure the kurtosis
  • C. 4th moment about the mean is used to measure the skewness
  • D. The median is used to measure the central tendency

Answer: D

 

NEW QUESTION 156
Reliability can be specified in terms of all of the following EXCEPT:
Response:

  • A. Cost of failure
  • B. Stress to failure.
  • C. Cycles to failure.
  • D. Time to failure.

Answer: A

 

NEW QUESTION 157
Design review should be a process to ensure and/or develop more reliable design. Which of the following person(s), if any, should work with the designer during the design process?
Response:

  • A. Design supervisor.
  • B. Reliability engineer.
  • C. Designer only
  • D. Management team.

Answer: B

 